Skip to content


Standpipe Systems and Operational Insights

No comments

The Fire Deparment Connection

 

There are some discussions emanating and emerging regarding the Medical Center Fire in Asheville, NC that claimed the life of a highly regarded Captain and injured numerous firefighters. Emerging reports are discussing water supply, standpipe operability and integrity and deployment delays affecting fire behavior, growth, intensive and operational risks during the time in which water was attempting to be delivered to hand lines extended on the fire floor of the Medical Center.

See coverage HERE on CommandSafety.com and HERE at the Asheville Citizens-Times.com today. Direct link HERE

The following links have been compiled that provide a variety of insights and perspectives on operations conducted with standpipe systems.

Two 1.5-inch attack lines off a gated wye (poor standpipe valve positioning - the second line probably would kink when charged). Technically, a 2.5-inch to 2.5-inch gated wye with reducers is better if a high-volume (2.5-inch) line is suddenly needed. Copyright © 2011 Massey Enterprises, Inc.

Delayed Standpipe Operations Investigated in Asheville Medical Building Fire

2 comments

Photo: C.J. Naum, 2010

 

Apparent delays with establishing a sustained water supply via the building standpipe system are being published in the Asheville Citizens-Times.com today. Direct link HERE

Published reports are indicating possible problems with water delivery to the standpipe system designed to supply water from a street hydrant system to the fifth floor of a burning medical office building likely delayed firefighters as they battled the deadly blaze, according to Fire Department radio transmissions.
Nearly 25 minutes passed from the time the first trucks left their stations about 12:30 p.m. Thursday until a company reported they were finally putting water on the blaze at 445 Biltmore Center from a ladder truck.

Typical Standpipe Stairwell Valve Connection

Firefighters repeatedly made references to a lack of water, even as they reached the fourth floor and made their way toward flames one floor above according to same publication. They are referencing transcripts from fireground radio transmissions. HERE.

  • Asheville NC Fatal FF Mayday Audio 7/28/11; The audio has been edited and most of the Mayday audio from the FF has been edited out

The lack of timely application of water as a suppression agent to disrupt the progressing fire growth and magnitude could contribute towards increased fire severity based upon the fire load package and heat release rate and likely contribute towards untenable interior conditions in the absence of a vent path and confinement of the escalating products of combustion due to fire growth.

  • Refer to the CommandSafety.com posting HERE with a typical floor layout plan and interior photos
  • Reports indicating delays and challenges in gaining access into various rooms and locations are also being reported whcih should be expected based upon typical medical office layouts and configurations.

Vent path considerations, when addressing interior suppression operations, ventilation profiles and avenues and fire and heat propagation all have considerations and applications when working a seated fire within a compartment fire in a commercial occupancy

Refer to the following links for some further insights on the aforementioned elements and factors;

 

 

Fire Location on the Number Five Floor. Medical Office Building Copyright 2011 Microscoft Pictometry Birdseye View Pictometry Intl. Corp

 

 

  •  PDFs On Standpipe Systems: HERE and HERE
  • San Diego Fire & LIfe Safety Services LINK HERE
  • FDNY Standpipe Operations, HERE
  • STANDPIPE SYSTEM OPERATIONS: ENGINE COMPANY BASICS BY ANDREW A. FREDERICKS, FDNY (1996),

 

Medical Office Building Multiple Alarm Fire Leds to Fire Captain LODD

1 comment

Medical Office Building A multiple 4-alarm fire took command of a medical office suite located in a five story non-sprinklered Medical Center Office Building in the City of Asheville, North Carolina on Thursday July 28, 2011.

The mid-day fire was reported on the fifth floor at 445 Biltmore Center medical offices and was found extending from exterior perimeter windows as arriving companies went to work.

According to published reports, companies encountered heavy smoke and heat conditions. As initial suppression operations were being conducted, coordinated search and rescue operations were assigned and being conducted.  AFD Capt. Jeff Bowen was among the first alarm assignment of firefighters to reach the building’s fire floor as unabated fire development and growth caused the perimeter windows to fail causing fire extension to the exterior and the induction of fresh air onto the fire floor. The intensity of the flame front and extension was evident as photographed out fifth-floor windows.

Fire Showing During primary search and rescue operations, approximately 45 minutes into the operations Captain Bowen transmitted a mayday for reasons undetermined at the present time. Heavy smoke and pronounced heat conditions filled that top floor, where he and fellow firefighter Jay Bettencourt were conducting search efforts.  Command quickly directed efforts to manage the mayday with companies deployed to support the RIT and mayday. There were reported sixty fire fighters assigned the suppression and rescue operations for the multiple alarms. About 200 patients and staff were in the building at the time of the fire.

Captain Jeff Bowen, Asheville FDPreliminary information suggests that Captain Bowen went into cardiac arrest after succumbing to intense smoke and heat, the city said in a statement released on Friday. Firefighter Bettencourt was transported to the Joseph M. Still Burn Center at Doctors Hospital in Augusta, Ga., for treatment. He was listed in critical condition Thursday night. Nine other firefighters were taken to the hospital in connection with the blaze. Six remained hospitalized late Thursday. Three were treated and released, according to Mission spokeswoman Merrell Gregory and published reports. Captain Bowen was a thirteen year fire service veteran and was a husband and father of three children. He was 37 years of age.

The Building comprising the occupancy at 445 Biltmore Center medical offices was occupied by the Cancer Care of WNC which had its laboratory and information and technology offices on the fifth floor.

The building was constructed in 1982 and was not required by codes to have a sprinkler system at the time of occupancy. Since that time, state code provisions have changed that mandate sprinkler system protection. There were no requirements for retrofitting according to published reports.

The five story building with non-combustible construction classification consisted of approximate 120,000 square feet of space with approximately 20,000 SF per floor level.  

Links